No meetings this week, just some physical progress to report!
Construction on the MRI room is progressing on schedule. What you see in the photos is prep work for the floor location that will support the weight of the MRI unit.
We poured the first layer of concrete last Friday. Once this cures, we’ll lay down a pre-fabricated channel for all the wiring. When the second layer of concrete is poured, the wiring channel will be embedded in the floor.

In addition, BMH received the draft for its storm water permit. We are in the process of reviewing the draft and hope to accept it soon. This is a critical piece of the permit process that we are looking forward to have in hand.
That’s all folks…
- Rob


Comments are closed.